FSA 489.126 (2) (a) and (b)

S
steve (at) gebelofflaw.com
Mon, Feb 23, 2015 1:53 PM

I have a situation where a contractor took  more than 10%  deposit and did not apply for permits for 5 months.  Judge  ruled in my client's favor  on Breach of contract count, but would not apply  489.126  because  the statute has the word and  ( meaning Court taking plain meaning  held part (b)  also had to be satisfied  " Start work within 90 days).  ( I am trying to  get a  the Court to find theft under part (4)…(4) Any person who violates any provision of this section is guilty of theft and shall be prosecuted and punished under s. 812.014.)

I belive Statute should say and/or .. In the scenario a contractor can take the deposit , never apply for permits  and be scott free.

I have not found any case law on this and  have been unable toresearch legislative history to get intent as too cost prohibitive for my client.

I argued to the Judge the legislative intent  was to protect  public ect..  Judge did not bite. Any advise or input . I believe clearly, this  needs to be changed in the Statute.

Thanks,

489.126 Moneys received by contractors.—

(1) For purposes of this section, the term “contractor” includes all definitions as set forth in s. 489.105http://www.leg.state.fl.us/Statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0400-0499/0489/Sections/0489.105.html(3), and any person performing or contracting or promising to perform work described therein, without regard to the licensure of the person.

(2) A contractor who receives, as initial payment, money totaling more than 10 percent of the contract price for repair, restoration, improvement, or construction to residential real property must:
(a) Apply for permits necessary to do work within 30 days after the date payment is made, except where the work does not require a permit under the applicable codes and ordinances, and

(b) Start the work within 90 days after the date all necessary permits for work, if any, are issued,

Stephen B. Gebeloff, Esq.

Stephen B. Gebeloff, P.A.
5255 North Federal Highway
Third Floor
Boca Raton, Florida  33487
(561)953-4600
Fax (561)953-4610
steve@gebelofflaw.commailto:steve@gebelofflaw.com
www.flcollectionattorney.comhttp://www.flcollectionattorney.com/
www.floridacollectionattorney.nethttp://www.floridacollectionattorney.net

I have a situation where a contractor took more than 10% deposit and did not apply for permits for 5 months. Judge ruled in my client's favor on Breach of contract count, but would not apply 489.126 because the statute has the word and ( meaning Court taking plain meaning held part (b) also had to be satisfied " Start work within 90 days). ( I am trying to get a the Court to find theft under part (4)…(4) Any person who violates any provision of this section is guilty of theft and shall be prosecuted and punished under s. 812.014.) I belive Statute should say and/or .. In the scenario a contractor can take the deposit , never apply for permits and be scott free. I have not found any case law on this and have been unable toresearch legislative history to get intent as too cost prohibitive for my client. I argued to the Judge the legislative intent was to protect public ect.. Judge did not bite. Any advise or input . I believe clearly, this needs to be changed in the Statute. Thanks, 489.126 Moneys received by contractors.— (1) For purposes of this section, the term “contractor” includes all definitions as set forth in s. 489.105<http://www.leg.state.fl.us/Statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0400-0499/0489/Sections/0489.105.html>(3), and any person performing or contracting or promising to perform work described therein, without regard to the licensure of the person. (2) A contractor who receives, as initial payment, money totaling more than 10 percent of the contract price for repair, restoration, improvement, or construction to residential real property must: (a) Apply for permits necessary to do work within 30 days after the date payment is made, except where the work does not require a permit under the applicable codes and ordinances, and (b) Start the work within 90 days after the date all necessary permits for work, if any, are issued, Stephen B. Gebeloff, Esq. Stephen B. Gebeloff, P.A. 5255 North Federal Highway Third Floor Boca Raton, Florida 33487 (561)953-4600 Fax (561)953-4610 steve@gebelofflaw.com<mailto:steve@gebelofflaw.com> www.flcollectionattorney.com<http://www.flcollectionattorney.com/> www.floridacollectionattorney.net<http://www.floridacollectionattorney.net>
FD
Fred Dudley
Mon, Feb 23, 2015 2:22 PM

The use of “and/or” is not followed by legislative drafters because it leads to further ambiguities. However, placing an “or” between (a) and (b) should work, don’t you think?

Fred R. Dudley, Partner
Board Certified Construction Lawyer
Dudley, Sellers & Healy, P. L.
SunTrust Financial Center, Suite 301
3522 Thomasville Road
Tallahassee, Florida 32308
Cell: (850) 294-3471
Direct: (850)692-6368
dudley@mylicenselaw.com

From: clc-discussion-bounces@lists.flabarrpptl.org [mailto:clc-discussion-bounces@lists.flabarrpptl.org] On Behalf Of steve@gebelofflaw.com
Sent: Monday, February 23, 2015 9:11 AM
To: clc-discussion@lists.flabarrpptl.org
Subject: [CLC-Discussion] FSA 489.126 (2) (a) and (b)

I have a situation where a contractor took  more than 10%  deposit and did not apply for permits for 5 months.  Judge  ruled in my client's favor  on Breach of contract count, but would not apply  489.126  because  the statute has the word and  ( meaning Court taking plain meaning  held part (b)  also had to be satisfied  " Start work within 90 days).  ( I am trying to  get a  the Court to find theft under part (4)…(4) Any person who violates any provision of this section is guilty of theft and shall be prosecuted and punished under s. 812.014.)

I belive Statute should say and/or .. In the scenario a contractor can take the deposit , never apply for permits  and be scott free.

I have not found any case law on this and  have been unable toresearch legislative history to get intent as too cost prohibitive for my client.

I argued to the Judge the legislative intent  was to protect  public ect..  Judge did not bite. Any advise or input . I believe clearly, this  needs to be changed in the Statute.

Thanks,

489.126 Moneys received by contractors.—

(1) For purposes of this section, the term “contractor” includes all definitions as set forth in s. 489.105http://www.leg.state.fl.us/Statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0400-0499/0489/Sections/0489.105.html(3), and any person performing or contracting or promising to perform work described therein, without regard to the licensure of the person.

(2) A contractor who receives, as initial payment, money totaling more than 10 percent of the contract price for repair, restoration, improvement, or construction to residential real property must:
(a) Apply for permits necessary to do work within 30 days after the date payment is made, except where the work does not require a permit under the applicable codes and ordinances, and

(b) Start the work within 90 days after the date all necessary permits for work, if any, are issued,

Stephen B. Gebeloff, Esq.

Stephen B. Gebeloff, P.A.
5255 North Federal Highway
Third Floor
Boca Raton, Florida  33487
(561)953-4600
Fax (561)953-4610
steve@gebelofflaw.commailto:steve@gebelofflaw.com
www.flcollectionattorney.comhttp://www.flcollectionattorney.com/
www.floridacollectionattorney.nethttp://www.floridacollectionattorney.net

The use of “and/or” is not followed by legislative drafters because it leads to further ambiguities. However, placing an “or” between (a) and (b) should work, don’t you think? Fred R. Dudley, Partner Board Certified Construction Lawyer Dudley, Sellers & Healy, P. L. SunTrust Financial Center, Suite 301 3522 Thomasville Road Tallahassee, Florida 32308 Cell: (850) 294-3471 Direct: (850)692-6368 dudley@mylicenselaw.com From: clc-discussion-bounces@lists.flabarrpptl.org [mailto:clc-discussion-bounces@lists.flabarrpptl.org] On Behalf Of steve@gebelofflaw.com Sent: Monday, February 23, 2015 9:11 AM To: clc-discussion@lists.flabarrpptl.org Subject: [CLC-Discussion] FSA 489.126 (2) (a) and (b) I have a situation where a contractor took more than 10% deposit and did not apply for permits for 5 months. Judge ruled in my client's favor on Breach of contract count, but would not apply 489.126 because the statute has the word and ( meaning Court taking plain meaning held part (b) also had to be satisfied " Start work within 90 days). ( I am trying to get a the Court to find theft under part (4)…(4) Any person who violates any provision of this section is guilty of theft and shall be prosecuted and punished under s. 812.014.) I belive Statute should say and/or .. In the scenario a contractor can take the deposit , never apply for permits and be scott free. I have not found any case law on this and have been unable toresearch legislative history to get intent as too cost prohibitive for my client. I argued to the Judge the legislative intent was to protect public ect.. Judge did not bite. Any advise or input . I believe clearly, this needs to be changed in the Statute. Thanks, 489.126 Moneys received by contractors.— (1) For purposes of this section, the term “contractor” includes all definitions as set forth in s. 489.105<http://www.leg.state.fl.us/Statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0400-0499/0489/Sections/0489.105.html>(3), and any person performing or contracting or promising to perform work described therein, without regard to the licensure of the person. (2) A contractor who receives, as initial payment, money totaling more than 10 percent of the contract price for repair, restoration, improvement, or construction to residential real property must: (a) Apply for permits necessary to do work within 30 days after the date payment is made, except where the work does not require a permit under the applicable codes and ordinances, and (b) Start the work within 90 days after the date all necessary permits for work, if any, are issued, Stephen B. Gebeloff, Esq. Stephen B. Gebeloff, P.A. 5255 North Federal Highway Third Floor Boca Raton, Florida 33487 (561)953-4600 Fax (561)953-4610 steve@gebelofflaw.com<mailto:steve@gebelofflaw.com> www.flcollectionattorney.com<http://www.flcollectionattorney.com/> www.floridacollectionattorney.net<http://www.floridacollectionattorney.net>
BP
Bruce Partington
Mon, Feb 23, 2015 2:53 PM

I agree with Fred that and/or should not be used (ever, really, but that’s my opinion). However I would argue that if the contractor doesn’t fulfill any of the requirements of 2(a) or (b) it has violated the statute. This paragraph (2) describes steps the contractor must take to comply with the statute (“contractor . . . must”) and the things it must do are conjunctive (a and b). To avoid violating the statute the contractor must do BOTH things.  If it has failed to do either, then it cannot meet the test of having complied with both. In other words, if it hasn’t done a, it cannot have complied with a requirement to do both a and b.

Think about it this way, the contractor gets one point for complying with a, and another for complying with b. The contractor violates the statute if it doesn’t have 2 points. If it does b but not a, the contractor will only have 1 point. Now, if the statute read “or” then the contractor could pass the test by having only 1 point (a or b).

Bruce D. Partington
Clark Partington
bpartington@cphlaw.commailto:bpartington@cphlaw.com
Direct: 850-432-1399
Fax: 850-432-7340
*Board Certified in Construction Law

From: clc-discussion-bounces@lists.flabarrpptl.org [mailto:clc-discussion-bounces@lists.flabarrpptl.org] On Behalf Of Fred Dudley
Sent: Monday, February 23, 2015 8:22 AM
To: steve@gebelofflaw.com; clc-discussion@lists.flabarrpptl.org
Subject: Re: [CLC-Discussion] FSA 489.126 (2) (a) and (b)

The use of “and/or” is not followed by legislative drafters because it leads to further ambiguities. However, placing an “or” between (a) and (b) should work, don’t you think?

Fred R. Dudley, Partner
Board Certified Construction Lawyer
Dudley, Sellers & Healy, P. L.
SunTrust Financial Center, Suite 301
3522 Thomasville Road
Tallahassee, Florida 32308
Cell: (850) 294-3471
Direct: (850)692-6368
dudley@mylicenselaw.com

From: clc-discussion-bounces@lists.flabarrpptl.org [mailto:clc-discussion-bounces@lists.flabarrpptl.org] On Behalf Of steve@gebelofflaw.com
Sent: Monday, February 23, 2015 9:11 AM
To: clc-discussion@lists.flabarrpptl.org
Subject: [CLC-Discussion] FSA 489.126 (2) (a) and (b)

I have a situation where a contractor took  more than 10%  deposit and did not apply for permits for 5 months.  Judge  ruled in my client's favor  on Breach of contract count, but would not apply  489.126  because  the statute has the word and  ( meaning Court taking plain meaning  held part (b)  also had to be satisfied  " Start work within 90 days).  ( I am trying to  get a  the Court to find theft under part (4)…(4) Any person who violates any provision of this section is guilty of theft and shall be prosecuted and punished under s. 812.014.)

I belive Statute should say and/or .. In the scenario a contractor can take the deposit , never apply for permits  and be scott free.

I have not found any case law on this and  have been unable toresearch legislative history to get intent as too cost prohibitive for my client.

I argued to the Judge the legislative intent  was to protect  public ect..  Judge did not bite. Any advise or input . I believe clearly, this  needs to be changed in the Statute.

Thanks,

489.126 Moneys received by contractors.—

(1) For purposes of this section, the term “contractor” includes all definitions as set forth in s. 489.105http://www.leg.state.fl.us/Statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0400-0499/0489/Sections/0489.105.html(3), and any person performing or contracting or promising to perform work described therein, without regard to the licensure of the person.

(2) A contractor who receives, as initial payment, money totaling more than 10 percent of the contract price for repair, restoration, improvement, or construction to residential real property must:
(a) Apply for permits necessary to do work within 30 days after the date payment is made, except where the work does not require a permit under the applicable codes and ordinances, and

(b) Start the work within 90 days after the date all necessary permits for work, if any, are issued,

Stephen B. Gebeloff, Esq.

Stephen B. Gebeloff, P.A.
5255 North Federal Highway
Third Floor
Boca Raton, Florida  33487
(561)953-4600
Fax (561)953-4610
steve@gebelofflaw.commailto:steve@gebelofflaw.com
www.flcollectionattorney.comhttp://www.flcollectionattorney.com/
www.floridacollectionattorney.nethttp://www.floridacollectionattorney.net

I agree with Fred that and/or should not be used (ever, really, but that’s my opinion). However I would argue that if the contractor doesn’t fulfill any of the requirements of 2(a) or (b) it has violated the statute. This paragraph (2) describes steps the contractor must take to comply with the statute (“contractor . . . must”) and the things it must do are conjunctive (a and b). To avoid violating the statute the contractor must do BOTH things. If it has failed to do either, then it cannot meet the test of having complied with both. In other words, if it hasn’t done a, it cannot have complied with a requirement to do both a and b. Think about it this way, the contractor gets one point for complying with a, and another for complying with b. The contractor violates the statute if it doesn’t have 2 points. If it does b but not a, the contractor will only have 1 point. Now, if the statute read “or” then the contractor could pass the test by having only 1 point (a or b). Bruce D. Partington Clark Partington bpartington@cphlaw.com<mailto:bpartington@cphlaw.com> Direct: 850-432-1399 Fax: 850-432-7340 *Board Certified in Construction Law From: clc-discussion-bounces@lists.flabarrpptl.org [mailto:clc-discussion-bounces@lists.flabarrpptl.org] On Behalf Of Fred Dudley Sent: Monday, February 23, 2015 8:22 AM To: steve@gebelofflaw.com; clc-discussion@lists.flabarrpptl.org Subject: Re: [CLC-Discussion] FSA 489.126 (2) (a) and (b) The use of “and/or” is not followed by legislative drafters because it leads to further ambiguities. However, placing an “or” between (a) and (b) should work, don’t you think? Fred R. Dudley, Partner Board Certified Construction Lawyer Dudley, Sellers & Healy, P. L. SunTrust Financial Center, Suite 301 3522 Thomasville Road Tallahassee, Florida 32308 Cell: (850) 294-3471 Direct: (850)692-6368 dudley@mylicenselaw.com From: clc-discussion-bounces@lists.flabarrpptl.org [mailto:clc-discussion-bounces@lists.flabarrpptl.org] On Behalf Of steve@gebelofflaw.com Sent: Monday, February 23, 2015 9:11 AM To: clc-discussion@lists.flabarrpptl.org Subject: [CLC-Discussion] FSA 489.126 (2) (a) and (b) I have a situation where a contractor took more than 10% deposit and did not apply for permits for 5 months. Judge ruled in my client's favor on Breach of contract count, but would not apply 489.126 because the statute has the word and ( meaning Court taking plain meaning held part (b) also had to be satisfied " Start work within 90 days). ( I am trying to get a the Court to find theft under part (4)…(4) Any person who violates any provision of this section is guilty of theft and shall be prosecuted and punished under s. 812.014.) I belive Statute should say and/or .. In the scenario a contractor can take the deposit , never apply for permits and be scott free. I have not found any case law on this and have been unable toresearch legislative history to get intent as too cost prohibitive for my client. I argued to the Judge the legislative intent was to protect public ect.. Judge did not bite. Any advise or input . I believe clearly, this needs to be changed in the Statute. Thanks, 489.126 Moneys received by contractors.— (1) For purposes of this section, the term “contractor” includes all definitions as set forth in s. 489.105<http://www.leg.state.fl.us/Statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0400-0499/0489/Sections/0489.105.html>(3), and any person performing or contracting or promising to perform work described therein, without regard to the licensure of the person. (2) A contractor who receives, as initial payment, money totaling more than 10 percent of the contract price for repair, restoration, improvement, or construction to residential real property must: (a) Apply for permits necessary to do work within 30 days after the date payment is made, except where the work does not require a permit under the applicable codes and ordinances, and (b) Start the work within 90 days after the date all necessary permits for work, if any, are issued, Stephen B. Gebeloff, Esq. Stephen B. Gebeloff, P.A. 5255 North Federal Highway Third Floor Boca Raton, Florida 33487 (561)953-4600 Fax (561)953-4610 steve@gebelofflaw.com<mailto:steve@gebelofflaw.com> www.flcollectionattorney.com<http://www.flcollectionattorney.com/> www.floridacollectionattorney.net<http://www.floridacollectionattorney.net>
WB
Wolf, Brian
Mon, Feb 23, 2015 3:01 PM

Steve:

The statute is fine. It requires the contractor to both apply within 30 days and start the work within 90 days of the permit issue date. Your facts show that the contractor satisfied one of two requirements; thus, the contractor violated the statute. Modifying the statute is not prudent.

From: clc-discussion-bounces@lists.flabarrpptl.org [mailto:clc-discussion-bounces@lists.flabarrpptl.org] On Behalf Of Fred Dudley
Sent: Monday, February 23, 2015 9:22 AM
To: steve@gebelofflaw.com; clc-discussion@lists.flabarrpptl.org
Subject: Re: [CLC-Discussion] FSA 489.126 (2) (a) and (b)

The use of “and/or” is not followed by legislative drafters because it leads to further ambiguities. However, placing an “or” between (a) and (b) should work, don’t you think?

Fred R. Dudley, Partner
Board Certified Construction Lawyer
Dudley, Sellers & Healy, P. L.
SunTrust Financial Center, Suite 301
3522 Thomasville Road
Tallahassee, Florida 32308
Cell: (850) 294-3471
Direct: (850)692-6368
dudley@mylicenselaw.commailto:dudley@mylicenselaw.com

From: clc-discussion-bounces@lists.flabarrpptl.org [mailto:clc-discussion-bounces@lists.flabarrpptl.org] On Behalf Of steve@gebelofflaw.com
Sent: Monday, February 23, 2015 9:11 AM
To: clc-discussion@lists.flabarrpptl.org
Subject: [CLC-Discussion] FSA 489.126 (2) (a) and (b)

I have a situation where a contractor took  more than 10%  deposit and did not apply for permits for 5 months.  Judge  ruled in my client's favor  on Breach of contract count, but would not apply  489.126  because  the statute has the word and  ( meaning Court taking plain meaning  held part (b)  also had to be satisfied  " Start work within 90 days).  ( I am trying to  get a  the Court to find theft under part (4)…(4) Any person who violates any provision of this section is guilty of theft and shall be prosecuted and punished under s. 812.014.)

I belive Statute should say and/or .. In the scenario a contractor can take the deposit , never apply for permits  and be scott free.

I have not found any case law on this and  have been unable toresearch legislative history to get intent as too cost prohibitive for my client.

I argued to the Judge the legislative intent  was to protect  public ect..  Judge did not bite. Any advise or input . I believe clearly, this  needs to be changed in the Statute.

Thanks,

489.126 Moneys received by contractors.—

(1) For purposes of this section, the term “contractor” includes all definitions as set forth in s. 489.105http://www.leg.state.fl.us/Statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0400-0499/0489/Sections/0489.105.html(3), and any person performing or contracting or promising to perform work described therein, without regard to the licensure of the person.

(2) A contractor who receives, as initial payment, money totaling more than 10 percent of the contract price for repair, restoration, improvement, or construction to residential real property must:
(a) Apply for permits necessary to do work within 30 days after the date payment is made, except where the work does not require a permit under the applicable codes and ordinances, and

(b) Start the work within 90 days after the date all necessary permits for work, if any, are issued,

Stephen B. Gebeloff, Esq.

Stephen B. Gebeloff, P.A.
5255 North Federal Highway
Third Floor
Boca Raton, Florida  33487
(561)953-4600
Fax (561)953-4610
steve@gebelofflaw.commailto:steve@gebelofflaw.com
www.flcollectionattorney.comhttp://www.flcollectionattorney.com/
www.floridacollectionattorney.nethttp://www.floridacollectionattorney.net

Steve: The statute is fine. It requires the contractor to both apply within 30 days and start the work within 90 days of the permit issue date. Your facts show that the contractor satisfied one of two requirements; thus, the contractor violated the statute. Modifying the statute is not prudent. From: clc-discussion-bounces@lists.flabarrpptl.org [mailto:clc-discussion-bounces@lists.flabarrpptl.org] On Behalf Of Fred Dudley Sent: Monday, February 23, 2015 9:22 AM To: steve@gebelofflaw.com; clc-discussion@lists.flabarrpptl.org Subject: Re: [CLC-Discussion] FSA 489.126 (2) (a) and (b) The use of “and/or” is not followed by legislative drafters because it leads to further ambiguities. However, placing an “or” between (a) and (b) should work, don’t you think? Fred R. Dudley, Partner Board Certified Construction Lawyer Dudley, Sellers & Healy, P. L. SunTrust Financial Center, Suite 301 3522 Thomasville Road Tallahassee, Florida 32308 Cell: (850) 294-3471 Direct: (850)692-6368 dudley@mylicenselaw.com<mailto:dudley@mylicenselaw.com> From: clc-discussion-bounces@lists.flabarrpptl.org [mailto:clc-discussion-bounces@lists.flabarrpptl.org] On Behalf Of steve@gebelofflaw.com Sent: Monday, February 23, 2015 9:11 AM To: clc-discussion@lists.flabarrpptl.org Subject: [CLC-Discussion] FSA 489.126 (2) (a) and (b) I have a situation where a contractor took more than 10% deposit and did not apply for permits for 5 months. Judge ruled in my client's favor on Breach of contract count, but would not apply 489.126 because the statute has the word and ( meaning Court taking plain meaning held part (b) also had to be satisfied " Start work within 90 days). ( I am trying to get a the Court to find theft under part (4)…(4) Any person who violates any provision of this section is guilty of theft and shall be prosecuted and punished under s. 812.014.) I belive Statute should say and/or .. In the scenario a contractor can take the deposit , never apply for permits and be scott free. I have not found any case law on this and have been unable toresearch legislative history to get intent as too cost prohibitive for my client. I argued to the Judge the legislative intent was to protect public ect.. Judge did not bite. Any advise or input . I believe clearly, this needs to be changed in the Statute. Thanks, 489.126 Moneys received by contractors.— (1) For purposes of this section, the term “contractor” includes all definitions as set forth in s. 489.105<http://www.leg.state.fl.us/Statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0400-0499/0489/Sections/0489.105.html>(3), and any person performing or contracting or promising to perform work described therein, without regard to the licensure of the person. (2) A contractor who receives, as initial payment, money totaling more than 10 percent of the contract price for repair, restoration, improvement, or construction to residential real property must: (a) Apply for permits necessary to do work within 30 days after the date payment is made, except where the work does not require a permit under the applicable codes and ordinances, and (b) Start the work within 90 days after the date all necessary permits for work, if any, are issued, Stephen B. Gebeloff, Esq. Stephen B. Gebeloff, P.A. 5255 North Federal Highway Third Floor Boca Raton, Florida 33487 (561)953-4600 Fax (561)953-4610 steve@gebelofflaw.com<mailto:steve@gebelofflaw.com> www.flcollectionattorney.com<http://www.flcollectionattorney.com/> www.floridacollectionattorney.net<http://www.floridacollectionattorney.net>
TM
Thomas M Dillon
Mon, Feb 23, 2015 3:06 PM

The statute says what the contractor must do: apply for permits within 30 days AND begin work within 90 days.  Those obligations should be, and are, stated in the conjunctive.  If the contractor does not comply with either of the requirements, the contractor should be liable.  I think the court simply misconstrued the statute, reading it as if it stated preconditions to suit, and then read them in the conjunctive.

Thomas M Dillon

Email: lawtmd@gmail.com

Florida Bar No. 673064

Thomas M Dillon, PA

1477 Park Beach Cir. Apt. 32

Punta Gorda, FL 33950-5252

Phone: 941-626-6832

From: clc-discussion-bounces@lists.flabarrpptl.org [mailto:clc-discussion-bounces@lists.flabarrpptl.org] On Behalf Of Fred Dudley
Sent: Monday, February 23, 2015 9:22 AM
To: steve@gebelofflaw.com; clc-discussion@lists.flabarrpptl.org
Subject: Re: [CLC-Discussion] FSA 489.126 (2) (a) and (b)

The use of “and/or” is not followed by legislative drafters because it leads to further ambiguities. However, placing an “or” between (a) and (b) should work, don’t you think?

Fred R. Dudley, Partner

Board Certified Construction Lawyer

Dudley, Sellers & Healy, P. L.

SunTrust Financial Center, Suite 301

3522 Thomasville Road

Tallahassee, Florida 32308

Cell: (850) 294-3471

Direct: (850)692-6368

dudley@mylicenselaw.com

From: clc-discussion-bounces@lists.flabarrpptl.org [mailto:clc-discussion-bounces@lists.flabarrpptl.org] On Behalf Of steve@gebelofflaw.com
Sent: Monday, February 23, 2015 9:11 AM
To: clc-discussion@lists.flabarrpptl.org
Subject: [CLC-Discussion] FSA 489.126 (2) (a) and (b)

I have a situation where a contractor took  more than 10%  deposit and did not apply for permits for 5 months.  Judge  ruled in my client's favor  on Breach of contract count, but would not apply  489.126  because  the statute has the word and  ( meaning Court taking plain meaning  held part (b)  also had to be satisfied  " Start work within 90 days).  ( I am trying to  get a  the Court to find theft under part (4)…(4) Any person who violates any provision of this section is guilty of theft and shall be prosecuted and punished under s. 812.014.)

I belive Statute should say and/or .. In the scenario a contractor can take the deposit , never apply for permits  and be scott free.

I have not found any case law on this and  have been unable toresearch legislative history to get intent as too cost prohibitive for my client.

I argued to the Judge the legislative intent  was to protect  public ect..  Judge did not bite. Any advise or input . I believe clearly, this  needs to be changed in the Statute.

Thanks,

489.126 Moneys received by contractors.—

(1) For purposes of this section, the term “contractor” includes all definitions as set forth in s. 489.105 http://www.leg.state.fl.us/Statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0400-0499/0489/Sections/0489.105.html (3), and any person performing or contracting or promising to perform work described therein, without regard to the licensure of the person.

(2) A contractor who receives, as initial payment, money totaling more than 10 percent of the contract price for repair, restoration, improvement, or construction to residential real property must:

(a) Apply for permits necessary to do work within 30 days after the date payment is made, except where the work does not require a permit under the applicable codes and ordinances, and

(b) Start the work within 90 days after the date all necessary permits for work, if any, are issued,

Stephen B. Gebeloff, Esq.

Stephen B. Gebeloff, P.A.

5255 North Federal Highway

Third Floor

Boca Raton, Florida  33487

(561)953-4600

Fax (561)953-4610

steve@gebelofflaw.com

www.flcollectionattorney.com http://www.flcollectionattorney.com/

www.floridacollectionattorney.net

The statute says what the contractor must do: apply for permits within 30 days AND begin work within 90 days. Those obligations should be, and are, stated in the conjunctive. If the contractor does not comply with either of the requirements, the contractor should be liable. I think the court simply misconstrued the statute, reading it as if it stated preconditions to suit, and then read them in the conjunctive. Thomas M Dillon Email: lawtmd@gmail.com Florida Bar No. 673064 Thomas M Dillon, PA 1477 Park Beach Cir. Apt. 32 Punta Gorda, FL 33950-5252 Phone: 941-626-6832 From: clc-discussion-bounces@lists.flabarrpptl.org [mailto:clc-discussion-bounces@lists.flabarrpptl.org] On Behalf Of Fred Dudley Sent: Monday, February 23, 2015 9:22 AM To: steve@gebelofflaw.com; clc-discussion@lists.flabarrpptl.org Subject: Re: [CLC-Discussion] FSA 489.126 (2) (a) and (b) The use of “and/or” is not followed by legislative drafters because it leads to further ambiguities. However, placing an “or” between (a) and (b) should work, don’t you think? Fred R. Dudley, Partner Board Certified Construction Lawyer Dudley, Sellers & Healy, P. L. SunTrust Financial Center, Suite 301 3522 Thomasville Road Tallahassee, Florida 32308 Cell: (850) 294-3471 Direct: (850)692-6368 dudley@mylicenselaw.com From: clc-discussion-bounces@lists.flabarrpptl.org [mailto:clc-discussion-bounces@lists.flabarrpptl.org] On Behalf Of steve@gebelofflaw.com Sent: Monday, February 23, 2015 9:11 AM To: clc-discussion@lists.flabarrpptl.org Subject: [CLC-Discussion] FSA 489.126 (2) (a) and (b) I have a situation where a contractor took more than 10% deposit and did not apply for permits for 5 months. Judge ruled in my client's favor on Breach of contract count, but would not apply 489.126 because the statute has the word and ( meaning Court taking plain meaning held part (b) also had to be satisfied " Start work within 90 days). ( I am trying to get a the Court to find theft under part (4)…(4) Any person who violates any provision of this section is guilty of theft and shall be prosecuted and punished under s. 812.014.) I belive Statute should say and/or .. In the scenario a contractor can take the deposit , never apply for permits and be scott free. I have not found any case law on this and have been unable toresearch legislative history to get intent as too cost prohibitive for my client. I argued to the Judge the legislative intent was to protect public ect.. Judge did not bite. Any advise or input . I believe clearly, this needs to be changed in the Statute. Thanks, 489.126 Moneys received by contractors.— (1) For purposes of this section, the term “contractor” includes all definitions as set forth in s. 489.105 <http://www.leg.state.fl.us/Statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0400-0499/0489/Sections/0489.105.html> (3), and any person performing or contracting or promising to perform work described therein, without regard to the licensure of the person. (2) A contractor who receives, as initial payment, money totaling more than 10 percent of the contract price for repair, restoration, improvement, or construction to residential real property must: (a) Apply for permits necessary to do work within 30 days after the date payment is made, except where the work does not require a permit under the applicable codes and ordinances, and (b) Start the work within 90 days after the date all necessary permits for work, if any, are issued, Stephen B. Gebeloff, Esq. Stephen B. Gebeloff, P.A. 5255 North Federal Highway Third Floor Boca Raton, Florida 33487 (561)953-4600 Fax (561)953-4610 steve@gebelofflaw.com www.flcollectionattorney.com <http://www.flcollectionattorney.com/> www.floridacollectionattorney.net