Construction Law Committee -: Surety & Insurance Subcommittee Report

AD
Arnold D. Tritt, Jr.
Mon, Sep 12, 2011 2:48 PM

Gang:  Sorry.  One more thing.  See attached the September case law
update from the Surety & Insurance subcommittee.  Arnie.

Arnold D. Tritt, Jr.
Board Certified Construction Attorney

707 Peninsular Place
Jacksonville, Florida 32204
Phone (904) 354-5200
Facsimile (904) 354-5256
Arnold.Tritt@atritt.com
www.tritthenderson.com

CONFIDENTIALITY NOTICE: The information and all attachments contained in this electronic communication are legally privileged and confidential information, subject to the attorney-client privilege and intended only for the use of intended recipients .  If the reader of this message is not an intended recipient, you are hereby notified that any review, use, dissemination, distribution or copying of this communication is strictly prohibited .  If you have received this communication in error, please notify us immediately of the error by return email and please permanently remove any copies of this message from your system and do not retain any copies, whether in electronic or physical form or otherwise .  Unauthorized interception of this e-mail is a violation of federal criminal law.

TAX ADVICE DISCLOSURE: Pursuant to the requirements of Internal Revenue Service Circular 230, we advise you that any federal tax advice contained in this communication (including any attachments) is not intended or written to be used, and cannot be used, for the purpose of: (1) avoiding penalties that maybe imposed under the Internal Revenue Code or (2) promoting, marketing or recommending to another party any transaction or matter addressed in this communication.

Disclaimer regarding Uniform Electronic Transactions Act ("UETA") (Florida Statutes Section 668.50): If this communication concerns negotiation of a contract or agreement, UETA does not apply to this communication; contract formation in this matter shall occur only with manually-affixed original signatures on original documents.

Gang: Sorry. One more thing. See attached the September case law update from the Surety & Insurance subcommittee. Arnie. Arnold D. Tritt, Jr. Board Certified Construction Attorney 707 Peninsular Place Jacksonville, Florida 32204 Phone (904) 354-5200 Facsimile (904) 354-5256 Arnold.Tritt@atritt.com www.tritthenderson.com CONFIDENTIALITY NOTICE: The information and all attachments contained in this electronic communication are legally privileged and confidential information, subject to the attorney-client privilege and intended only for the use of intended recipients . If the reader of this message is not an intended recipient, you are hereby notified that any review, use, dissemination, distribution or copying of this communication is strictly prohibited . If you have received this communication in error, please notify us immediately of the error by return email and please permanently remove any copies of this message from your system and do not retain any copies, whether in electronic or physical form or otherwise . Unauthorized interception of this e-mail is a violation of federal criminal law. TAX ADVICE DISCLOSURE: Pursuant to the requirements of Internal Revenue Service Circular 230, we advise you that any federal tax advice contained in this communication (including any attachments) is not intended or written to be used, and cannot be used, for the purpose of: (1) avoiding penalties that maybe imposed under the Internal Revenue Code or (2) promoting, marketing or recommending to another party any transaction or matter addressed in this communication. Disclaimer regarding Uniform Electronic Transactions Act ("UETA") (Florida Statutes Section 668.50): If this communication concerns negotiation of a contract or agreement, UETA does not apply to this communication; contract formation in this matter shall occur only with manually-affixed original signatures on original documents.
PW
Peyton White Lumpkin
Mon, Sep 12, 2011 2:57 PM

Hi Arnie, to whom do I speak to change my email address for the listserv? I
have another I use for this kind of thing so it's not so distracting---
thanks!

Peyton White Lumpkin, Esq., LEED AP

The Lumpkin Law Firm P.A.

2655 Le Jeune Road

Fifth Floor

Coral Gables, FL 33134

Tel: (305) 667-1808

Fax: (305) 444-5366

peytonwhitelumpkin@bellsouth.net

thelumpkinlawfirm.com

Confidentiality Notice:  This e-mail message, including any attachments, is
for the sole use of the intended recipient and may contain confidential and
privileged information.  Any unauthorized review, use, disclosure or
distribution is prohibited.  If you are not the intended recipient, please
contact the sender by reply e-mail and destroy all copies of the original
message, including all attachments.


From: constructionlaw-bounces@lists.flabarrpptl.org
[mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Arnold
D. Tritt, Jr.
Sent: Monday, September 12, 2011 10:49 AM
To: constructionlaw@lists.flabarrpptl.org
Subject: [RPPTL-constructionlaw] Construction Law Committee -: Surety &
Insurance Subcommittee Report

Gang:  Sorry.  One more thing.  See attached the September case law update
from the Surety & Insurance subcommittee.  Arnie.

Arnold D. Tritt, Jr.

Board Certified Construction Attorney

707 Peninsular Place
Jacksonville, Florida 32204

Phone (904) 354-5200
Facsimile (904) 354-5256
Arnold.Tritt@atritt.com  mailto:%5Be-mail%5D
www.tritthenderson.com http://www.tritthenderson.com/

CONFIDENTIALITY NOTICE: The information and all attachments contained in
this electronic communication are legally privileged and confidential
information, subject to the attorney-client privilege and intended only for
the use of intended recipients. If the reader of this message is not an
intended recipient, you are hereby notified that any review, use,
dissemination, distribution or copying of this communication is strictly
prohibited. If you have received this communication in error, please notify
us immediately of the error by return email and please permanently remove
any copies of this message from your system and do not retain any copies,
whether in electronic or physical form or otherwise. Unauthorized
interception of this e-mail is a violation of federal criminal law.

TAX ADVICE DISCLOSURE: Pursuant to the requirements of Internal Revenue
Service Circular 230, we advise you that any federal tax advice contained in
this communication (including any attachments) is not intended or written to
be used, and cannot be used, for the purpose of: (1) avoiding penalties that
maybe imposed under the Internal Revenue Code or (2) promoting, marketing or
recommending to another party any transaction or matter addressed in this
communication.

Disclaimer regarding Uniform Electronic Transactions Act ("UETA") (Florida
Statutes Section 668.50): If this communication concerns negotiation of a
contract or agreement, UETA does not apply to this communication; contract
formation in this matter shall occur only with manually-affixed original
signatures on original documents.

Hi Arnie, to whom do I speak to change my email address for the listserv? I have another I use for this kind of thing so it's not so distracting--- thanks! Peyton White Lumpkin, Esq., LEED AP The Lumpkin Law Firm P.A. 2655 Le Jeune Road Fifth Floor Coral Gables, FL 33134 Tel: (305) 667-1808 Fax: (305) 444-5366 peytonwhitelumpkin@bellsouth.net thelumpkinlawfirm.com Confidentiality Notice: This e-mail message, including any attachments, is for the sole use of the intended recipient and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient, please contact the sender by reply e-mail and destroy all copies of the original message, including all attachments. _____ From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Arnold D. Tritt, Jr. Sent: Monday, September 12, 2011 10:49 AM To: constructionlaw@lists.flabarrpptl.org Subject: [RPPTL-constructionlaw] Construction Law Committee -: Surety & Insurance Subcommittee Report Gang: Sorry. One more thing. See attached the September case law update from the Surety & Insurance subcommittee. Arnie. Arnold D. Tritt, Jr. Board Certified Construction Attorney 707 Peninsular Place Jacksonville, Florida 32204 Phone (904) 354-5200 Facsimile (904) 354-5256 Arnold.Tritt@atritt.com <mailto:%5Be-mail%5D> www.tritthenderson.com <http://www.tritthenderson.com/> CONFIDENTIALITY NOTICE: The information and all attachments contained in this electronic communication are legally privileged and confidential information, subject to the attorney-client privilege and intended only for the use of intended recipients. If the reader of this message is not an intended recipient, you are hereby notified that any review, use, dissemination, distribution or copying of this communication is strictly prohibited. If you have received this communication in error, please notify us immediately of the error by return email and please permanently remove any copies of this message from your system and do not retain any copies, whether in electronic or physical form or otherwise. Unauthorized interception of this e-mail is a violation of federal criminal law. TAX ADVICE DISCLOSURE: Pursuant to the requirements of Internal Revenue Service Circular 230, we advise you that any federal tax advice contained in this communication (including any attachments) is not intended or written to be used, and cannot be used, for the purpose of: (1) avoiding penalties that maybe imposed under the Internal Revenue Code or (2) promoting, marketing or recommending to another party any transaction or matter addressed in this communication. Disclaimer regarding Uniform Electronic Transactions Act ("UETA") (Florida Statutes Section 668.50): If this communication concerns negotiation of a contract or agreement, UETA does not apply to this communication; contract formation in this matter shall occur only with manually-affixed original signatures on original documents.
AF
Andrea Fair
Thu, Sep 29, 2011 1:57 PM

I represent a contractor who furnished ground stabilization related to sinkhole activity.  My client has a lien on the property for the work.  The insurance company has cut a check payable to the owner, my client, and the mortgage lender.  The owner’s attorney is holding the check but is trying to get the insurance company to drop the owner’s name from the check and reissue a new check (I suppose to avoid any involvement in a dispute between my client and the lender for the insurance proceeds).  The owner is also considering interpleader.  The lender has requested that the owner endorse the check and send it to them and then they will consider what to do with it from there.  The owner does not want to do that because they feel the lender will not release the funds to my client and then the owner still has liability to my client.  The mortgage was recorded before the NOC for my client’s work.  The mortgage provides that insurance proceeds will be applied to restoration or repair of the property if it is economically feasible and lender’s security is not lessened.  Any suggestions on how to proceed from this point?

Andrea M. Fair-Purcell
Board Certified Construction Attorney
▬▬▬▬▬▬▬▬▬▬▬▬
FAIR•LAW•PLLC
▬▬▬▬▬▬▬▬▬▬▬▬
13046 Racetrack Road #236
Tampa, FL 33626
(813) 412-1077 phone
(877) 879-4990 fax
www.fairconstructionliens.com

The contents of this e-mail message and any attachments are intended solely for the addressee(s) named in this e-mail message. This communication is intended to be and to remain confidential and may be subject to applicable attorney/client and/or work product privileges. If you are not the intended recipient of this e-mail message, or if this e-mail message has been addressed to you in error, please immediately alert the sender by reply e-mail and then delete this e-mail message and its attachments. Do not deliver, distribute or copy this e-mail message and/or any attachments and if you are not the intended recipient, do not disclose the contents or take any action in reliance upon the information contained in this communication or any attachments.

I represent a contractor who furnished ground stabilization related to sinkhole activity. My client has a lien on the property for the work. The insurance company has cut a check payable to the owner, my client, and the mortgage lender. The owner’s attorney is holding the check but is trying to get the insurance company to drop the owner’s name from the check and reissue a new check (I suppose to avoid any involvement in a dispute between my client and the lender for the insurance proceeds). The owner is also considering interpleader. The lender has requested that the owner endorse the check and send it to them and then they will consider what to do with it from there. The owner does not want to do that because they feel the lender will not release the funds to my client and then the owner still has liability to my client. The mortgage was recorded before the NOC for my client’s work. The mortgage provides that insurance proceeds will be applied to restoration or repair of the property if it is economically feasible and lender’s security is not lessened. Any suggestions on how to proceed from this point? Andrea M. Fair-Purcell Board Certified Construction Attorney ▬▬▬▬▬▬▬▬▬▬▬▬ FAIR•LAW•PLLC ▬▬▬▬▬▬▬▬▬▬▬▬ 13046 Racetrack Road #236 Tampa, FL 33626 (813) 412-1077 phone (877) 879-4990 fax www.fairconstructionliens.com The contents of this e-mail message and any attachments are intended solely for the addressee(s) named in this e-mail message. This communication is intended to be and to remain confidential and may be subject to applicable attorney/client and/or work product privileges. If you are not the intended recipient of this e-mail message, or if this e-mail message has been addressed to you in error, please immediately alert the sender by reply e-mail and then delete this e-mail message and its attachments. Do not deliver, distribute or copy this e-mail message and/or any attachments and if you are not the intended recipient, do not disclose the contents or take any action in reliance upon the information contained in this communication or any attachments.
TM
Tom McKeel
Thu, Sep 29, 2011 2:11 PM

Interpleader or Dec. Action.  It doesn’t sound like the insurance company and the lender will agree to very much. Let a judge decide.


From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Andrea Fair
Sent: Thursday, September 29, 2011 9:58 AM
To: RPPTL constructionlaw
Subject: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds

I represent a contractor who furnished ground stabilization related to sinkhole activity.  My client has a lien on the property for the work.  The insurance company has cut a check payable to the owner, my client, and the mortgage lender.  The owner’s attorney is holding the check but is trying to get the insurance company to drop the owner’s name from the check and reissue a new check (I suppose to avoid any involvement in a dispute between my client and the lender for the insurance proceeds).  The owner is also considering interpleader.  The lender has requested that the owner endorse the check and send it to them and then they will consider what to do with it from there.  The owner does not want to do that because they feel the lender will not release the funds to my client and then the owner still has liability to my client.  The mortgage was recorded before the NOC for my client’s work.  The mortgage provides that insurance proceeds will be applied to restoration or repair of the property if it is economically feasible and lender’s security is not lessened.  Any suggestions on how to proceed from this point?

Andrea M. Fair-Purcell

Board Certified Construction Attorney

▬▬▬▬▬▬▬▬▬▬▬▬

FAIR•LAW•PLLC

▬▬▬▬▬▬▬▬▬▬▬▬
13046 Racetrack Road #236
Tampa, FL 33626
(813) 412-1077 phone
(877) 879-4990 fax
www.fairconstructionliens.com

The contents of this e-mail message and any attachments are intended solely for the addressee(s) named in this e-mail message. This communication is intended to be and to remain confidential and may be subject to applicable attorney/client and/or work product privileges. If you are not the intended recipient of this e-mail message, or if this e-mail message has been addressed to you in error, please immediately alert the sender by reply e-mail and then delete this e-mail message and its attachments. Do not deliver, distribute or copy this e-mail message and/or any attachments and if you are not the intended recipient, do not disclose the contents or take any action in reliance upon the information contained in this communication or any attachments.

Interpleader or Dec. Action. It doesn’t sound like the insurance company and the lender will agree to very much. Let a judge decide. _____ From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Andrea Fair Sent: Thursday, September 29, 2011 9:58 AM To: RPPTL constructionlaw Subject: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds I represent a contractor who furnished ground stabilization related to sinkhole activity. My client has a lien on the property for the work. The insurance company has cut a check payable to the owner, my client, and the mortgage lender. The owner’s attorney is holding the check but is trying to get the insurance company to drop the owner’s name from the check and reissue a new check (I suppose to avoid any involvement in a dispute between my client and the lender for the insurance proceeds). The owner is also considering interpleader. The lender has requested that the owner endorse the check and send it to them and then they will consider what to do with it from there. The owner does not want to do that because they feel the lender will not release the funds to my client and then the owner still has liability to my client. The mortgage was recorded before the NOC for my client’s work. The mortgage provides that insurance proceeds will be applied to restoration or repair of the property if it is economically feasible and lender’s security is not lessened. Any suggestions on how to proceed from this point? Andrea M. Fair-Purcell Board Certified Construction Attorney ▬▬▬▬▬▬▬▬▬▬▬▬ FAIR•LAW•PLLC ▬▬▬▬▬▬▬▬▬▬▬▬ 13046 Racetrack Road #236 Tampa, FL 33626 (813) 412-1077 phone (877) 879-4990 fax www.fairconstructionliens.com The contents of this e-mail message and any attachments are intended solely for the addressee(s) named in this e-mail message. This communication is intended to be and to remain confidential and may be subject to applicable attorney/client and/or work product privileges. If you are not the intended recipient of this e-mail message, or if this e-mail message has been addressed to you in error, please immediately alert the sender by reply e-mail and then delete this e-mail message and its attachments. Do not deliver, distribute or copy this e-mail message and/or any attachments and if you are not the intended recipient, do not disclose the contents or take any action in reliance upon the information contained in this communication or any attachments.
LL
Larry Leiby
Thu, Sep 29, 2011 2:18 PM

Andrea,

You may want to make the owner and lender aware that your client also has a lien on the insurance proceeds pursuant to F.S. 713.32.  It sounds like your lien is inferior to the lien of the lender, but the lender also needs to be made aware of your claims (against the proceeds and the property).  The lender should cooperate if it has been timely paid.  If not ….  Interpleader will likely end up in the owner seeking fees.  If you file your action to enforce against the property and the insurance proceeds and you are successful, the owner should not be able to claim fees. See 457 So.2d 597.

Larry R. Leiby, Esq.
Malka & Kravitz, P.A.
1300 Sawgrass Corp. Pkwy., Suite 100
Ft. Lauderdale, FL  33323
Phone:  954-514-0984
Fax:      954-514-0985

e-mail:  leiby@mkpalaw.com

Board Certified in Construction Law
Fla. S. Ct. Certified Circuit Court Civil Mediator
Fellow, College of Commercial Arbitrators

From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Andrea Fair
Sent: Thursday, September 29, 2011 9:58 AM
To: RPPTL constructionlaw
Subject: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds

I represent a contractor who furnished ground stabilization related to sinkhole activity.  My client has a lien on the property for the work.  The insurance company has cut a check payable to the owner, my client, and the mortgage lender.  The owner’s attorney is holding the check but is trying to get the insurance company to drop the owner’s name from the check and reissue a new check (I suppose to avoid any involvement in a dispute between my client and the lender for the insurance proceeds).  The owner is also considering interpleader.  The lender has requested that the owner endorse the check and send it to them and then they will consider what to do with it from there.  The owner does not want to do that because they feel the lender will not release the funds to my client and then the owner still has liability to my client.  The mortgage was recorded before the NOC for my client’s work.  The mortgage provides that insurance proceeds will be applied to restoration or repair of the property if it is economically feasible and lender’s security is not lessened.  Any suggestions on how to proceed from this point?

Andrea M. Fair-Purcell
Board Certified Construction Attorney
▬▬▬▬▬▬▬▬▬▬▬▬
FAIR•LAW•PLLC
▬▬▬▬▬▬▬▬▬▬▬▬
13046 Racetrack Road #236
Tampa, FL 33626
(813) 412-1077 phone
(877) 879-4990 fax
www.fairconstructionliens.com

The contents of this e-mail message and any attachments are intended solely for the addressee(s) named in this e-mail message. This communication is intended to be and to remain confidential and may be subject to applicable attorney/client and/or work product privileges. If you are not the intended recipient of this e-mail message, or if this e-mail message has been addressed to you in error, please immediately alert the sender by reply e-mail and then delete this e-mail message and its attachments. Do not deliver, distribute or copy this e-mail message and/or any attachments and if you are not the intended recipient, do not disclose the contents or take any action in reliance upon the information contained in this communication or any attachments.

Andrea, You may want to make the owner and lender aware that your client also has a lien on the insurance proceeds pursuant to F.S. 713.32. It sounds like your lien is inferior to the lien of the lender, but the lender also needs to be made aware of your claims (against the proceeds and the property). The lender should cooperate if it has been timely paid. If not …. Interpleader will likely end up in the owner seeking fees. If you file your action to enforce against the property and the insurance proceeds and you are successful, the owner should not be able to claim fees. See 457 So.2d 597. Larry R. Leiby, Esq. Malka & Kravitz, P.A. 1300 Sawgrass Corp. Pkwy., Suite 100 Ft. Lauderdale, FL 33323 Phone: 954-514-0984 Fax: 954-514-0985 e-mail: leiby@mkpalaw.com Board Certified in Construction Law Fla. S. Ct. Certified Circuit Court Civil Mediator Fellow, College of Commercial Arbitrators From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Andrea Fair Sent: Thursday, September 29, 2011 9:58 AM To: RPPTL constructionlaw Subject: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds I represent a contractor who furnished ground stabilization related to sinkhole activity. My client has a lien on the property for the work. The insurance company has cut a check payable to the owner, my client, and the mortgage lender. The owner’s attorney is holding the check but is trying to get the insurance company to drop the owner’s name from the check and reissue a new check (I suppose to avoid any involvement in a dispute between my client and the lender for the insurance proceeds). The owner is also considering interpleader. The lender has requested that the owner endorse the check and send it to them and then they will consider what to do with it from there. The owner does not want to do that because they feel the lender will not release the funds to my client and then the owner still has liability to my client. The mortgage was recorded before the NOC for my client’s work. The mortgage provides that insurance proceeds will be applied to restoration or repair of the property if it is economically feasible and lender’s security is not lessened. Any suggestions on how to proceed from this point? Andrea M. Fair-Purcell Board Certified Construction Attorney ▬▬▬▬▬▬▬▬▬▬▬▬ FAIR•LAW•PLLC ▬▬▬▬▬▬▬▬▬▬▬▬ 13046 Racetrack Road #236 Tampa, FL 33626 (813) 412-1077 phone (877) 879-4990 fax www.fairconstructionliens.com The contents of this e-mail message and any attachments are intended solely for the addressee(s) named in this e-mail message. This communication is intended to be and to remain confidential and may be subject to applicable attorney/client and/or work product privileges. If you are not the intended recipient of this e-mail message, or if this e-mail message has been addressed to you in error, please immediately alert the sender by reply e-mail and then delete this e-mail message and its attachments. Do not deliver, distribute or copy this e-mail message and/or any attachments and if you are not the intended recipient, do not disclose the contents or take any action in reliance upon the information contained in this communication or any attachments.
ST
Steve Thompson
Thu, Sep 29, 2011 2:28 PM

Andrea,

Take a look at 713.32 addressing an insurer's obligations under this scenario.

Steven F. Thompson, Esq.
Thompson & Brooks
412 E. Madison St., Ste 900
Tampa, Fl. 33602
813-387-1821
Fax 813-387-1824

THE ABOVE MAY CONTAIN OR CONSTITUTE A  CONFIDENTIAL
AND PRIVILEGED COMMUNICATION. IF YOU ARE NOT THE INTENDED
RECIPIENT, OR IF YOU HAVE OTHERWISE RECEIVED THIS COMMUNICATION
IN ERROR, PLEASE NOTIFY THE OFFICE OF THOMPSON & BROOKS BY TELEPHONE
AT (813) 387-1821 [collect] AND INFORM THE OFFICE OF THE ERROR;
AND PLEASE DESTROY OR DELETE THIS MESSAGE. THIS MESSAGE MAY NOT
BE REVIEWED, PRINTED, DISPLAYED, OR RE-TRANSMITTED WITHOUT THE
SENDER'S CONSENT. ALL RIGHTS PROTECTED. THERE MAY BE NO FURTHER
DISTRIBUTION OR PUBLICATION OF THIS COMMUNICATION OR ITS CONTENTS
WITHOUT THE EXPRESS CONSENT OF THOMPSON & BROOKS. THANK YOU.


From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Andrea Fair
Sent: Thursday, September 29, 2011 9:58 AM
To: RPPTL constructionlaw
Subject: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds

I represent a contractor who furnished ground stabilization related to sinkhole activity.  My client has a lien on the property for the work.  The insurance company has cut a check payable to the owner, my client, and the mortgage lender.  The owner’s attorney is holding the check but is trying to get the insurance company to drop the owner’s name from the check and reissue a new check (I suppose to avoid any involvement in a dispute between my client and the lender for the insurance proceeds).  The owner is also considering interpleader.  The lender has requested that the owner endorse the check and send it to them and then they will consider what to do with it from there.  The owner does not want to do that because they feel the lender will not release the funds to my client and then the owner still has liability to my client.  The mortgage was recorded before the NOC for my client’s work.  The mortgage provides that insurance proceeds will be applied to restoration or repair of the property if it is economically feasible and lender’s security is not lessened.  Any suggestions on how to proceed from this point?

Andrea M. Fair-Purcell

Board Certified Construction Attorney

▬▬▬▬▬▬▬▬▬▬▬▬

FAIR•LAW•PLLC

▬▬▬▬▬▬▬▬▬▬▬▬
13046 Racetrack Road #236
Tampa, FL 33626
(813) 412-1077 phone
(877) 879-4990 fax
www.fairconstructionliens.com

The contents of this e-mail message and any attachments are intended solely for the addressee(s) named in this e-mail message. This communication is intended to be and to remain confidential and may be subject to applicable attorney/client and/or work product privileges. If you are not the intended recipient of this e-mail message, or if this e-mail message has been addressed to you in error, please immediately alert the sender by reply e-mail and then delete this e-mail message and its attachments. Do not deliver, distribute or copy this e-mail message and/or any attachments and if you are not the intended recipient, do not disclose the contents or take any action in reliance upon the information contained in this communication or any attachments.

Andrea, Take a look at 713.32 addressing an insurer's obligations under this scenario. Steven F. Thompson, Esq. Thompson & Brooks 412 E. Madison St., Ste 900 Tampa, Fl. 33602 813-387-1821 Fax 813-387-1824 THE ABOVE MAY CONTAIN OR CONSTITUTE A CONFIDENTIAL AND PRIVILEGED COMMUNICATION. IF YOU ARE NOT THE INTENDED RECIPIENT, OR IF YOU HAVE OTHERWISE RECEIVED THIS COMMUNICATION IN ERROR, PLEASE NOTIFY THE OFFICE OF THOMPSON & BROOKS BY TELEPHONE AT (813) 387-1821 [collect] AND INFORM THE OFFICE OF THE ERROR; AND PLEASE DESTROY OR DELETE THIS MESSAGE. THIS MESSAGE MAY NOT BE REVIEWED, PRINTED, DISPLAYED, OR RE-TRANSMITTED WITHOUT THE SENDER'S CONSENT. ALL RIGHTS PROTECTED. THERE MAY BE NO FURTHER DISTRIBUTION OR PUBLICATION OF THIS COMMUNICATION OR ITS CONTENTS WITHOUT THE EXPRESS CONSENT OF THOMPSON & BROOKS. THANK YOU. _____ From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Andrea Fair Sent: Thursday, September 29, 2011 9:58 AM To: RPPTL constructionlaw Subject: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds I represent a contractor who furnished ground stabilization related to sinkhole activity. My client has a lien on the property for the work. The insurance company has cut a check payable to the owner, my client, and the mortgage lender. The owner’s attorney is holding the check but is trying to get the insurance company to drop the owner’s name from the check and reissue a new check (I suppose to avoid any involvement in a dispute between my client and the lender for the insurance proceeds). The owner is also considering interpleader. The lender has requested that the owner endorse the check and send it to them and then they will consider what to do with it from there. The owner does not want to do that because they feel the lender will not release the funds to my client and then the owner still has liability to my client. The mortgage was recorded before the NOC for my client’s work. The mortgage provides that insurance proceeds will be applied to restoration or repair of the property if it is economically feasible and lender’s security is not lessened. Any suggestions on how to proceed from this point? Andrea M. Fair-Purcell Board Certified Construction Attorney ▬▬▬▬▬▬▬▬▬▬▬▬ FAIR•LAW•PLLC ▬▬▬▬▬▬▬▬▬▬▬▬ 13046 Racetrack Road #236 Tampa, FL 33626 (813) 412-1077 phone (877) 879-4990 fax www.fairconstructionliens.com The contents of this e-mail message and any attachments are intended solely for the addressee(s) named in this e-mail message. This communication is intended to be and to remain confidential and may be subject to applicable attorney/client and/or work product privileges. If you are not the intended recipient of this e-mail message, or if this e-mail message has been addressed to you in error, please immediately alert the sender by reply e-mail and then delete this e-mail message and its attachments. Do not deliver, distribute or copy this e-mail message and/or any attachments and if you are not the intended recipient, do not disclose the contents or take any action in reliance upon the information contained in this communication or any attachments.
GM
Gibbons, Michael
Thu, Sep 29, 2011 2:56 PM

Per Fla. Stat. s. 627.707(5)(c) governing sinkhole related claims, the insurer is required to obtain the "written approval" of both the insured and the lender prior to making payment to the contractor.  Insurer is legally compelled to either issue the check for endorsement of all or otherwise get the approval in writing of owner and lender prior to making payment to contractor.  Alternatively, per terms of most property policies,  the insurer may issue check jointly to insured and lienholder of record (typically designated as a "loss payee" under the policy).  Either way, the path to resolution obviously runs through the lender.

It would appear that the real issue relates to the value looking forward of the newly stabilized property. If the effect of the stabilization work is to restore the value of the collateral, then the lender should not be able to glom the proceeds.  On other hand, if the property after stabilization is still devalued materially from where it was prior to sinkhole activity, then the lender may have a legitimate claim to the insurance proceeds.  Appears to me that it may come down to some appraisal opinions.  Regrettably, sounds like a real tar baby for all involved.

Michael R. Gibbons  (Bio http://lowndes-law.com/our-people/michael-r-gibbons )
Shareholder
Lowndes, Drosdick, Doster, Kantor & Reed, P.A.
450 South Orange Avenue, 8th Floor
Orlando, FL 32801
Phone: 407-418-6378
Fax: 407-843-4444
email: michael.gibbons@lowndes-law.com mailto:michael.gibbons@lowndes-law.com
website: http://www.lowndes-law.com http://www.lowndes-law.com/


From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Andrea Fair
Sent: Thursday, September 29, 2011 9:58 AM
To: RPPTL constructionlaw
Subject: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds

I represent a contractor who furnished ground stabilization related to sinkhole activity.  My client has a lien on the property for the work.  The insurance company has cut a check payable to the owner, my client, and the mortgage lender.  The owner’s attorney is holding the check but is trying to get the insurance company to drop the owner’s name from the check and reissue a new check (I suppose to avoid any involvement in a dispute between my client and the lender for the insurance proceeds).  The owner is also considering interpleader.  The lender has requested that the owner endorse the check and send it to them and then they will consider what to do with it from there.  The owner does not want to do that because they feel the lender will not release the funds to my client and then the owner still has liability to my client.  The mortgage was recorded before the NOC for my client’s work.  The mortgage provides that insurance proceeds will be applied to restoration or repair of the property if it is economically feasible and lender’s security is not lessened.  Any suggestions on how to proceed from this point?

Andrea M. Fair-Purcell

Board Certified Construction Attorney

▬▬▬▬▬▬▬▬▬▬▬▬

FAIR•LAW•PLLC

▬▬▬▬▬▬▬▬▬▬▬▬
13046 Racetrack Road #236
Tampa, FL 33626
(813) 412-1077 phone
(877) 879-4990 fax
www.fairconstructionliens.com

The contents of this e-mail message and any attachments are intended solely for the addressee(s) named in this e-mail message. This communication is intended to be and to remain confidential and may be subject to applicable attorney/client and/or work product privileges. If you are not the intended recipient of this e-mail message, or if this e-mail message has been addressed to you in error, please immediately alert the sender by reply e-mail and then delete this e-mail message and its attachments. Do not deliver, distribute or copy this e-mail message and/or any attachments and if you are not the intended recipient, do not disclose the contents or take any action in reliance upon the information contained in this communication or any attachments.

This email message has been delivered safely and archived online by Mimecast.  For more information please visit http://www.mimecast.com

Per Fla. Stat. s. 627.707(5)(c) governing sinkhole related claims, the insurer is required to obtain the "written approval" of both the insured and the lender prior to making payment to the contractor. Insurer is legally compelled to either issue the check for endorsement of all or otherwise get the approval in writing of owner and lender prior to making payment to contractor. Alternatively, per terms of most property policies, the insurer may issue check jointly to insured and lienholder of record (typically designated as a "loss payee" under the policy). Either way, the path to resolution obviously runs through the lender. It would appear that the real issue relates to the value looking forward of the newly stabilized property. If the effect of the stabilization work is to restore the value of the collateral, then the lender should not be able to glom the proceeds. On other hand, if the property after stabilization is still devalued materially from where it was prior to sinkhole activity, then the lender may have a legitimate claim to the insurance proceeds. Appears to me that it may come down to some appraisal opinions. Regrettably, sounds like a real tar baby for all involved. Michael R. Gibbons (Bio <http://lowndes-law.com/our-people/michael-r-gibbons> ) Shareholder Lowndes, Drosdick, Doster, Kantor & Reed, P.A. 450 South Orange Avenue, 8th Floor Orlando, FL 32801 Phone: 407-418-6378 Fax: 407-843-4444 email: michael.gibbons@lowndes-law.com <mailto:michael.gibbons@lowndes-law.com> website: http://www.lowndes-law.com <http://www.lowndes-law.com/> ________________________________ From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Andrea Fair Sent: Thursday, September 29, 2011 9:58 AM To: RPPTL constructionlaw Subject: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds I represent a contractor who furnished ground stabilization related to sinkhole activity. My client has a lien on the property for the work. The insurance company has cut a check payable to the owner, my client, and the mortgage lender. The owner’s attorney is holding the check but is trying to get the insurance company to drop the owner’s name from the check and reissue a new check (I suppose to avoid any involvement in a dispute between my client and the lender for the insurance proceeds). The owner is also considering interpleader. The lender has requested that the owner endorse the check and send it to them and then they will consider what to do with it from there. The owner does not want to do that because they feel the lender will not release the funds to my client and then the owner still has liability to my client. The mortgage was recorded before the NOC for my client’s work. The mortgage provides that insurance proceeds will be applied to restoration or repair of the property if it is economically feasible and lender’s security is not lessened. Any suggestions on how to proceed from this point? Andrea M. Fair-Purcell Board Certified Construction Attorney ▬▬▬▬▬▬▬▬▬▬▬▬ FAIR•LAW•PLLC ▬▬▬▬▬▬▬▬▬▬▬▬ 13046 Racetrack Road #236 Tampa, FL 33626 (813) 412-1077 phone (877) 879-4990 fax www.fairconstructionliens.com The contents of this e-mail message and any attachments are intended solely for the addressee(s) named in this e-mail message. This communication is intended to be and to remain confidential and may be subject to applicable attorney/client and/or work product privileges. If you are not the intended recipient of this e-mail message, or if this e-mail message has been addressed to you in error, please immediately alert the sender by reply e-mail and then delete this e-mail message and its attachments. Do not deliver, distribute or copy this e-mail message and/or any attachments and if you are not the intended recipient, do not disclose the contents or take any action in reliance upon the information contained in this communication or any attachments. This email message has been delivered safely and archived online by Mimecast. For more information please visit http://www.mimecast.com
GM
Gibbons, Michael
Thu, Sep 29, 2011 3:10 PM
Re applicability of Fla. Stat. s. 713.32, it appears that the last sentence of that statute renders the section inapplicable where, as here, there is a mortgagee with a lien perfected prior to recording of NOC.

Michael R. Gibbons  (Bio http://lowndes-law.com/our-people/michael-r-gibbons )
Shareholder
Lowndes, Drosdick, Doster, Kantor & Reed, P.A.
450 South Orange Avenue, 8th Floor
Orlando, FL 32801
Phone: 407-418-6378
Fax: 407-843-4444
email: michael.gibbons@lowndes-law.com mailto:michael.gibbons@lowndes-law.com
website: http://www.lowndes-law.com http://www.lowndes-law.com/


From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Larry Leiby
Sent: Thursday, September 29, 2011 10:19 AM
To: RPPTL constructionlaw
Subject: Re: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds

Andrea,

You may want to make the owner and lender aware that your client also has a lien on the insurance proceeds pursuant to F.S. 713.32.  It sounds like your lien is inferior to the lien of the lender, but the lender also needs to be made aware of your claims (against the proceeds and the property).  The lender should cooperate if it has been timely paid.  If not ….  Interpleader will likely end up in the owner seeking fees.  If you file your action to enforce against the property and the insurance proceeds and you are successful, the owner should not be able to claim fees. See 457 So.2d 597.

Larry R. Leiby, Esq.

Malka & Kravitz, P.A.

1300 Sawgrass Corp. Pkwy., Suite 100

Ft. Lauderdale, FL  33323

Phone:  954-514-0984

Fax:      954-514-0985

e-mail:  leiby@mkpalaw.com

Board Certified in Construction Law

Fla. S. Ct. Certified Circuit Court Civil Mediator

Fellow, College of Commercial Arbitrators

From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Andrea Fair
Sent: Thursday, September 29, 2011 9:58 AM
To: RPPTL constructionlaw
Subject: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds

I represent a contractor who furnished ground stabilization related to sinkhole activity.  My client has a lien on the property for the work.  The insurance company has cut a check payable to the owner, my client, and the mortgage lender.  The owner’s attorney is holding the check but is trying to get the insurance company to drop the owner’s name from the check and reissue a new check (I suppose to avoid any involvement in a dispute between my client and the lender for the insurance proceeds).  The owner is also considering interpleader.  The lender has requested that the owner endorse the check and send it to them and then they will consider what to do with it from there.  The owner does not want to do that because they feel the lender will not release the funds to my client and then the owner still has liability to my client.  The mortgage was recorded before the NOC for my client’s work.  The mortgage provides that insurance proceeds will be applied to restoration or repair of the property if it is economically feasible and lender’s security is not lessened.  Any suggestions on how to proceed from this point?

Andrea M. Fair-Purcell

Board Certified Construction Attorney

▬▬▬▬▬▬▬▬▬▬▬▬

FAIR•LAW•PLLC

▬▬▬▬▬▬▬▬▬▬▬▬
13046 Racetrack Road #236
Tampa, FL 33626
(813) 412-1077 phone
(877) 879-4990 fax
www.fairconstructionliens.com

The contents of this e-mail message and any attachments are intended solely for the addressee(s) named in this e-mail message. This communication is intended to be and to remain confidential and may be subject to applicable attorney/client and/or work product privileges. If you are not the intended recipient of this e-mail message, or if this e-mail message has been addressed to you in error, please immediately alert the sender by reply e-mail and then delete this e-mail message and its attachments. Do not deliver, distribute or copy this e-mail message and/or any attachments and if you are not the intended recipient, do not disclose the contents or take any action in reliance upon the information contained in this communication or any attachments.

This email message has been delivered safely and archived online by Mimecast.  For more information please visit http://www.mimecast.com

Re applicability of Fla. Stat. s. 713.32, it appears that the last sentence of that statute renders the section inapplicable where, as here, there is a mortgagee with a lien perfected prior to recording of NOC. Michael R. Gibbons (Bio <http://lowndes-law.com/our-people/michael-r-gibbons> ) Shareholder Lowndes, Drosdick, Doster, Kantor & Reed, P.A. 450 South Orange Avenue, 8th Floor Orlando, FL 32801 Phone: 407-418-6378 Fax: 407-843-4444 email: michael.gibbons@lowndes-law.com <mailto:michael.gibbons@lowndes-law.com> website: http://www.lowndes-law.com <http://www.lowndes-law.com/> ________________________________ From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Larry Leiby Sent: Thursday, September 29, 2011 10:19 AM To: RPPTL constructionlaw Subject: Re: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds Andrea, You may want to make the owner and lender aware that your client also has a lien on the insurance proceeds pursuant to F.S. 713.32. It sounds like your lien is inferior to the lien of the lender, but the lender also needs to be made aware of your claims (against the proceeds and the property). The lender should cooperate if it has been timely paid. If not …. Interpleader will likely end up in the owner seeking fees. If you file your action to enforce against the property and the insurance proceeds and you are successful, the owner should not be able to claim fees. See 457 So.2d 597. Larry R. Leiby, Esq. Malka & Kravitz, P.A. 1300 Sawgrass Corp. Pkwy., Suite 100 Ft. Lauderdale, FL 33323 Phone: 954-514-0984 Fax: 954-514-0985 e-mail: leiby@mkpalaw.com Board Certified in Construction Law Fla. S. Ct. Certified Circuit Court Civil Mediator Fellow, College of Commercial Arbitrators From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Andrea Fair Sent: Thursday, September 29, 2011 9:58 AM To: RPPTL constructionlaw Subject: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds I represent a contractor who furnished ground stabilization related to sinkhole activity. My client has a lien on the property for the work. The insurance company has cut a check payable to the owner, my client, and the mortgage lender. The owner’s attorney is holding the check but is trying to get the insurance company to drop the owner’s name from the check and reissue a new check (I suppose to avoid any involvement in a dispute between my client and the lender for the insurance proceeds). The owner is also considering interpleader. The lender has requested that the owner endorse the check and send it to them and then they will consider what to do with it from there. The owner does not want to do that because they feel the lender will not release the funds to my client and then the owner still has liability to my client. The mortgage was recorded before the NOC for my client’s work. The mortgage provides that insurance proceeds will be applied to restoration or repair of the property if it is economically feasible and lender’s security is not lessened. Any suggestions on how to proceed from this point? Andrea M. Fair-Purcell Board Certified Construction Attorney ▬▬▬▬▬▬▬▬▬▬▬▬ FAIR•LAW•PLLC ▬▬▬▬▬▬▬▬▬▬▬▬ 13046 Racetrack Road #236 Tampa, FL 33626 (813) 412-1077 phone (877) 879-4990 fax www.fairconstructionliens.com The contents of this e-mail message and any attachments are intended solely for the addressee(s) named in this e-mail message. This communication is intended to be and to remain confidential and may be subject to applicable attorney/client and/or work product privileges. If you are not the intended recipient of this e-mail message, or if this e-mail message has been addressed to you in error, please immediately alert the sender by reply e-mail and then delete this e-mail message and its attachments. Do not deliver, distribute or copy this e-mail message and/or any attachments and if you are not the intended recipient, do not disclose the contents or take any action in reliance upon the information contained in this communication or any attachments. This email message has been delivered safely and archived online by Mimecast. For more information please visit http://www.mimecast.com
LL
Larry Leiby
Thu, Sep 29, 2011 3:40 PM

I would agree if the check were payable only to the mortgagee.  As I said, you are still going to be inferior to the prior lien of the mortgagee, but to the extent that the mortgagee doesn’t claim against the funds, and since the check is not payable only to the mortgagee, the claim may still have limited merit.

Larry R. Leiby, Esq.
Malka & Kravitz, P.A.
1300 Sawgrass Corp. Pkwy., Suite 100
Ft. Lauderdale, FL  33323
Phone:  954-514-0984
Fax:      954-514-0985

e-mail:  leiby@mkpalaw.com

Board Certified in Construction Law
Fla. S. Ct. Certified Circuit Court Civil Mediator
Fellow, College of Commercial Arbitrators

From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Gibbons, Michael
Sent: Thursday, September 29, 2011 11:11 AM
To: RPPTL constructionlaw
Subject: Re: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds

Re applicability of Fla. Stat. s. 713.32, it appears that the last sentence of that statute renders the section inapplicable where, as here, there is a mortgagee with a lien perfected prior to recording of NOC.

Michael R. Gibbons  (Biohttp://lowndes-law.com/our-people/michael-r-gibbons)
Shareholder
Lowndes, Drosdick, Doster, Kantor & Reed, P.A.
450 South Orange Avenue, 8th Floor
Orlando, FL 32801
Phone: 407-418-6378
Fax: 407-843-4444
email: michael.gibbons@lowndes-law.commailto:michael.gibbons@lowndes-law.com
website: http://www.lowndes-law.comhttp://www.lowndes-law.com/

 [cid:image001.jpg@01CC7E9C.A3F8A0C0]

From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Larry Leiby
Sent: Thursday, September 29, 2011 10:19 AM
To: RPPTL constructionlaw
Subject: Re: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds
Andrea,

You may want to make the owner and lender aware that your client also has a lien on the insurance proceeds pursuant to F.S. 713.32.  It sounds like your lien is inferior to the lien of the lender, but the lender also needs to be made aware of your claims (against the proceeds and the property).  The lender should cooperate if it has been timely paid.  If not ….  Interpleader will likely end up in the owner seeking fees.  If you file your action to enforce against the property and the insurance proceeds and you are successful, the owner should not be able to claim fees. See 457 So.2d 597.

Larry R. Leiby, Esq.
Malka & Kravitz, P.A.
1300 Sawgrass Corp. Pkwy., Suite 100
Ft. Lauderdale, FL  33323
Phone:  954-514-0984
Fax:      954-514-0985

e-mail:  leiby@mkpalaw.com

Board Certified in Construction Law
Fla. S. Ct. Certified Circuit Court Civil Mediator
Fellow, College of Commercial Arbitrators

From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Andrea Fair
Sent: Thursday, September 29, 2011 9:58 AM
To: RPPTL constructionlaw
Subject: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds

I represent a contractor who furnished ground stabilization related to sinkhole activity.  My client has a lien on the property for the work.  The insurance company has cut a check payable to the owner, my client, and the mortgage lender.  The owner’s attorney is holding the check but is trying to get the insurance company to drop the owner’s name from the check and reissue a new check (I suppose to avoid any involvement in a dispute between my client and the lender for the insurance proceeds).  The owner is also considering interpleader.  The lender has requested that the owner endorse the check and send it to them and then they will consider what to do with it from there.  The owner does not want to do that because they feel the lender will not release the funds to my client and then the owner still has liability to my client.  The mortgage was recorded before the NOC for my client’s work.  The mortgage provides that insurance proceeds will be applied to restoration or repair of the property if it is economically feasible and lender’s security is not lessened.  Any suggestions on how to proceed from this point?

Andrea M. Fair-Purcell
Board Certified Construction Attorney
▬▬▬▬▬▬▬▬▬▬▬▬
FAIR•LAW•PLLC
▬▬▬▬▬▬▬▬▬▬▬▬
13046 Racetrack Road #236
Tampa, FL 33626
(813) 412-1077 phone
(877) 879-4990 fax
www.fairconstructionliens.com

The contents of this e-mail message and any attachments are intended solely for the addressee(s) named in this e-mail message. This communication is intended to be and to remain confidential and may be subject to applicable attorney/client and/or work product privileges. If you are not the intended recipient of this e-mail message, or if this e-mail message has been addressed to you in error, please immediately alert the sender by reply e-mail and then delete this e-mail message and its attachments. Do not deliver, distribute or copy this e-mail message and/or any attachments and if you are not the intended recipient, do not disclose the contents or take any action in reliance upon the information contained in this communication or any attachments.

Notice of Confidentiality: This e-mail communication and the attachment(s) hereto, if any, are intended solely for the information and use of the addressee(s) identified above and may contain information which is legally privileged from disclosure and/or otherwise confidential. If a recipient of this e-mail communication is not an addressee (or an authorized representative of an addressee), such recipient is hereby advised that any review, disclosure, reproduction, re-transmission or other dissemination or use of this e-mail communication (or any information contained herein) is strictly prohibited. If you are not an addressee and have received this e-mail communication in error, please advise the sender of that circumstance either by reply e-mail or by telephone at (800) 356-6818, immediately delete this e-mail communication from any computer and destroy all physical copies of same.

Replies Filtered: Any incoming reply to this e-mail communication or other e-mail communication to us will be electronically filtered for "spam" and/or "viruses." That filtering process may result in such reply or other e-mail communications to us being quarantined (i.e., potentially not received at our site at all) and/or delayed in reaching us. For that reason, we cannot guarantee that we will receive your reply or other e-mail communications to us and/or that we will receive the same in a timely manner. Accordingly, you should consider sending communications to us which are particularly important or time-sensitive by means other than e-mail.

Notice Under U.S. Treasury Department Circular 230: To the extent that this e-mail communication and the attachment(s) hereto, if any, may contain written advice concerning or relating to a Federal (U.S.) tax issue, United States Treasury Department Regulations (Circular 230) require that we (and we do hereby) advise and disclose to you that, unless we expressly state otherwise in writing, such tax advice is not written or intended to be used, and cannot be used by you (the addressee), or other person(s), for purposes of (1) avoiding penalties imposed under the United States Internal Revenue Code or (2) promoting, marketing or recommending to any other person(s) the (or any of the) transaction(s) or matter(s) addressed, discussed or referenced herein. Each taxpayer should seek advice from an independent tax advisor with respect to any Federal tax issue(s), transaction(s) or matter(s) addressed, discussed or referenced herein based upon his, her or its particular circumstances. [v4.30]

I would agree if the check were payable only to the mortgagee. As I said, you are still going to be inferior to the prior lien of the mortgagee, but to the extent that the mortgagee doesn’t claim against the funds, and since the check is not payable only to the mortgagee, the claim may still have limited merit. Larry R. Leiby, Esq. Malka & Kravitz, P.A. 1300 Sawgrass Corp. Pkwy., Suite 100 Ft. Lauderdale, FL 33323 Phone: 954-514-0984 Fax: 954-514-0985 e-mail: leiby@mkpalaw.com Board Certified in Construction Law Fla. S. Ct. Certified Circuit Court Civil Mediator Fellow, College of Commercial Arbitrators From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Gibbons, Michael Sent: Thursday, September 29, 2011 11:11 AM To: RPPTL constructionlaw Subject: Re: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds Re applicability of Fla. Stat. s. 713.32, it appears that the last sentence of that statute renders the section inapplicable where, as here, there is a mortgagee with a lien perfected prior to recording of NOC. Michael R. Gibbons (Bio<http://lowndes-law.com/our-people/michael-r-gibbons>) Shareholder Lowndes, Drosdick, Doster, Kantor & Reed, P.A. 450 South Orange Avenue, 8th Floor Orlando, FL 32801 Phone: 407-418-6378 Fax: 407-843-4444 email: michael.gibbons@lowndes-law.com<mailto:michael.gibbons@lowndes-law.com> website: http://www.lowndes-law.com<http://www.lowndes-law.com/> [cid:image001.jpg@01CC7E9C.A3F8A0C0] ________________________________ From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Larry Leiby Sent: Thursday, September 29, 2011 10:19 AM To: RPPTL constructionlaw Subject: Re: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds Andrea, You may want to make the owner and lender aware that your client also has a lien on the insurance proceeds pursuant to F.S. 713.32. It sounds like your lien is inferior to the lien of the lender, but the lender also needs to be made aware of your claims (against the proceeds and the property). The lender should cooperate if it has been timely paid. If not …. Interpleader will likely end up in the owner seeking fees. If you file your action to enforce against the property and the insurance proceeds and you are successful, the owner should not be able to claim fees. See 457 So.2d 597. Larry R. Leiby, Esq. Malka & Kravitz, P.A. 1300 Sawgrass Corp. Pkwy., Suite 100 Ft. Lauderdale, FL 33323 Phone: 954-514-0984 Fax: 954-514-0985 e-mail: leiby@mkpalaw.com Board Certified in Construction Law Fla. S. Ct. Certified Circuit Court Civil Mediator Fellow, College of Commercial Arbitrators From: constructionlaw-bounces@lists.flabarrpptl.org [mailto:constructionlaw-bounces@lists.flabarrpptl.org] On Behalf Of Andrea Fair Sent: Thursday, September 29, 2011 9:58 AM To: RPPTL constructionlaw Subject: [RPPTL-constructionlaw] question re: priority of claims to insurance proceeds I represent a contractor who furnished ground stabilization related to sinkhole activity. My client has a lien on the property for the work. The insurance company has cut a check payable to the owner, my client, and the mortgage lender. The owner’s attorney is holding the check but is trying to get the insurance company to drop the owner’s name from the check and reissue a new check (I suppose to avoid any involvement in a dispute between my client and the lender for the insurance proceeds). The owner is also considering interpleader. The lender has requested that the owner endorse the check and send it to them and then they will consider what to do with it from there. The owner does not want to do that because they feel the lender will not release the funds to my client and then the owner still has liability to my client. The mortgage was recorded before the NOC for my client’s work. The mortgage provides that insurance proceeds will be applied to restoration or repair of the property if it is economically feasible and lender’s security is not lessened. Any suggestions on how to proceed from this point? Andrea M. Fair-Purcell Board Certified Construction Attorney ▬▬▬▬▬▬▬▬▬▬▬▬ FAIR•LAW•PLLC ▬▬▬▬▬▬▬▬▬▬▬▬ 13046 Racetrack Road #236 Tampa, FL 33626 (813) 412-1077 phone (877) 879-4990 fax www.fairconstructionliens.com The contents of this e-mail message and any attachments are intended solely for the addressee(s) named in this e-mail message. This communication is intended to be and to remain confidential and may be subject to applicable attorney/client and/or work product privileges. If you are not the intended recipient of this e-mail message, or if this e-mail message has been addressed to you in error, please immediately alert the sender by reply e-mail and then delete this e-mail message and its attachments. Do not deliver, distribute or copy this e-mail message and/or any attachments and if you are not the intended recipient, do not disclose the contents or take any action in reliance upon the information contained in this communication or any attachments. Notice of Confidentiality: This e-mail communication and the attachment(s) hereto, if any, are intended solely for the information and use of the addressee(s) identified above and may contain information which is legally privileged from disclosure and/or otherwise confidential. If a recipient of this e-mail communication is not an addressee (or an authorized representative of an addressee), such recipient is hereby advised that any review, disclosure, reproduction, re-transmission or other dissemination or use of this e-mail communication (or any information contained herein) is strictly prohibited. If you are not an addressee and have received this e-mail communication in error, please advise the sender of that circumstance either by reply e-mail or by telephone at (800) 356-6818, immediately delete this e-mail communication from any computer and destroy all physical copies of same. Replies Filtered: Any incoming reply to this e-mail communication or other e-mail communication to us will be electronically filtered for "spam" and/or "viruses." That filtering process may result in such reply or other e-mail communications to us being quarantined (i.e., potentially not received at our site at all) and/or delayed in reaching us. For that reason, we cannot guarantee that we will receive your reply or other e-mail communications to us and/or that we will receive the same in a timely manner. Accordingly, you should consider sending communications to us which are particularly important or time-sensitive by means other than e-mail. Notice Under U.S. Treasury Department Circular 230: To the extent that this e-mail communication and the attachment(s) hereto, if any, may contain written advice concerning or relating to a Federal (U.S.) tax issue, United States Treasury Department Regulations (Circular 230) require that we (and we do hereby) advise and disclose to you that, unless we expressly state otherwise in writing, such tax advice is not written or intended to be used, and cannot be used by you (the addressee), or other person(s), for purposes of (1) avoiding penalties imposed under the United States Internal Revenue Code or (2) promoting, marketing or recommending to any other person(s) the (or any of the) transaction(s) or matter(s) addressed, discussed or referenced herein. Each taxpayer should seek advice from an independent tax advisor with respect to any Federal tax issue(s), transaction(s) or matter(s) addressed, discussed or referenced herein based upon his, her or its particular circumstances. [v4.30]
CB
Charles B. Hernicz, Esq
Thu, Sep 29, 2011 4:31 PM

What is the meaning of the following language in FS 713.23(2) concerning a "Notice of Bond": "The notice shall be verified."  I have not been able to find any case law.  I interpret it as meaning verified by the surety that the bond is, indeed, valid an in effect.  A bond was recorded with the NOC, but the NOC expired before the project was complete, and, in an abundance of caution, I filed both a Notice of Nonpayment and a claim of lien.  The owner's attorney signed and recorded a "Notice of Bond" and attached a copy of the bond that was recorded with the NOC.  Does that satisfy the "verified" requirement and does this constitute a transfer of the lien to bond?

Chuck

Charles B. Hernicz, Esq.
Board Certified in Construction Law by The Florida Bar
Hernicz Legal Services, P.L.
15854 Bent Creek Road
Wellington, FL 33414
Telephone: (561) 753-7511
Facsimile: (561) 753-7082
Chernicz@HerniczLegal.com

What is the meaning of the following language in FS 713.23(2) concerning a "Notice of Bond": "The notice shall be verified." I have not been able to find any case law. I interpret it as meaning verified by the surety that the bond is, indeed, valid an in effect. A bond was recorded with the NOC, but the NOC expired before the project was complete, and, in an abundance of caution, I filed both a Notice of Nonpayment and a claim of lien. The owner's attorney signed and recorded a "Notice of Bond" and attached a copy of the bond that was recorded with the NOC. Does that satisfy the "verified" requirement and does this constitute a transfer of the lien to bond? Chuck Charles B. Hernicz, Esq. Board Certified in Construction Law by The Florida Bar Hernicz Legal Services, P.L. 15854 Bent Creek Road Wellington, FL 33414 Telephone: (561) 753-7511 Facsimile: (561) 753-7082 Chernicz@HerniczLegal.com